All pavement work is now complete, and crews will demobilize from the project over the long holiday weekend.
Beginning Monday, crews will return to focus on driveway construction, trail work near Awesome Car Wash, and corridor-wide backfilling activities. Crews from Davenport Electric will also continue installing streetlights over the next several weeks, with all streetlights expected to be in place by December 18.
Weather permitting, the north leg of the roundabout, including the intersection of 19th Street and 15th Avenue South, is expected to open to traffic by December 21.
A winter shutdown is anticipated around the holiday season. Clinton Engineering Company and BWC Excavating will return in spring 2027 to complete the remaining project elements, including South 17th Street construction, bike trails, sidewalks, and landscaping improvements. The project remains on schedule for completion by May 31, 2027.
The City of Clinton appreciates the public’s patience and cooperation as work continues during the Manufacturing Drive Improvement Project.
______________________________________________________________________
Please don’t hesitate to reach out to the City Engineering Department at any time at 563-244-3423 or email
jasoncraft@cityofclintoniowa.gov
zanepennock@cityofclintoniowa.gov
Bluff Boulevard Reconstruction Project Update
Construction crews from KE Flatwork will continue working between College Avenue and South 14th Street through the remainder of the 2026 construction season, with work expected to continue until winter weather suspends operations.
Over the next 3-4 weeks, crews are expected to complete the following work:
· Concrete pavement at the Bluff Heights Road intersection (November 30 through December 11)
· Storm sewer installation between Bluff Heights Road and Cornerstone Wellness (December 7 through December 11)
· Retaining Walls between Bluff Heights Road and College Avenue (until Christmas)
Completion of the concrete pavement between Bluff Heights Road and Cornerstone Wellness is contingent upon favorable weather conditions throughout December. If temperatures remain suitable for concrete construction, this work could be completed by Christmas.
Sewer crews are expected to continue working between Cornerstone Wellness and Bluff Elementary School well into the winter months. The city and contractor are currently exploring options for temporary pavement in this area to improve access and travel during the winter season.
As soon as weather conditions allow in spring 2027, the contractor will begin construction of the South 14th Street roundabout.
Looking ahead, KE Flatwork will significantly expand operations over the next two construction seasons as reconstruction progresses between South 14th Street and 7th Avenue North. Future work includes construction of a new roundabout at Springdale Drive and full roadway reconstruction throughout the corridor.
Please don’t hesitate to reach out to the City Engineering Department at any time at 563-244-3423 or email